After the Rite of Acceptance at Mass officially enrolled our 6th and 7th graders as Candidates for Confirmation, they are seen here gathering with their sponsors to discuss the sponsors' critical role and to break open God's Word. Each Of the Confirmandi were given a new youth study edition of the Bible.
Sunday, October 20, 2013
Saturday, October 5, 2013
Working the Budget
Just a status report, really. Design Development has progressed to the point that we can start getting more solid numbers regarding budgeting. Early on, design aimed at our target budget but necessarily vaguely. As design becomes more detailed, so can cost estimates.
As announced before, Poettker Construction of Breese, Illinois is helping us assess cost and constructability. As experienced contractors familiar with our area, they can not only provide good estimates but also recommend cost-reduction options where appropriate.
This Thursday a meeting was held with Msgr. Lawler and Fr. Beatty, Keith Poettker and Tom Arentsen of Poettker Construction, and Ethan Anthony and Kevin Hogan of Cram & Ferguson. We were joined at times by engineers and subcontractors. We put in a long, productive day and are a big step closer to finalizing design.
As this process unfolded, Cram and Ferguson presented a modification to design that will save a huge amount of money without unduly harming the beauty and integrity of our design. The building committee found this modification desirable and elegant. Before, the walls were very high, reaching as high as the vaulted ceiling. A peaked roof rose up from that level. The result was a magnificent upward extension to the building's exterior, but also a great deal of unused space in the attic. This was necessary to achieve the vaulted ceiling.
By moving to a peaked wood ceiling, we are able to eliminate that unused attic space. That means that without much change to the interior dimensions, we are lowering the exterior significantly. It also means a single row of windows rather than a large and small row. The eaves will still be about 24' high with the roof rising from there; I don't think anyone will call this a short building.
I think a finished wood ceiling with attractive beam work will be very beautiful. I look forward to sharing updated drawings with you as they become available.
We still have work to do and calculations are ongoing. Admittedly, this stage of our project has its frustrations, but overall I'm pleased with how it's going. Before we were looking at a stunning design and vaguely hoping we could achieve something like it on budget. Now, we've had to take some cost-reduction measures, but we're still looking at an amazing design. And now, we're much more certain that we're on track to achieve it.
Here's a very quickly produced sketch of the modification we've adopted. The walls are lower; the interior now extends up to the peak instead of being entirely within the height of the eaves. In this design the peak of the interior is actually several feet higher than with the vaults, but the outside height is reduced. This one change introduced a cascade of savings that were really needed to hit our budget.
Note: This sketch also reflects a look at a different transept window configuration. We've elected to stay with the rose window design there.
As announced before, Poettker Construction of Breese, Illinois is helping us assess cost and constructability. As experienced contractors familiar with our area, they can not only provide good estimates but also recommend cost-reduction options where appropriate.
This Thursday a meeting was held with Msgr. Lawler and Fr. Beatty, Keith Poettker and Tom Arentsen of Poettker Construction, and Ethan Anthony and Kevin Hogan of Cram & Ferguson. We were joined at times by engineers and subcontractors. We put in a long, productive day and are a big step closer to finalizing design.
As this process unfolded, Cram and Ferguson presented a modification to design that will save a huge amount of money without unduly harming the beauty and integrity of our design. The building committee found this modification desirable and elegant. Before, the walls were very high, reaching as high as the vaulted ceiling. A peaked roof rose up from that level. The result was a magnificent upward extension to the building's exterior, but also a great deal of unused space in the attic. This was necessary to achieve the vaulted ceiling.
By moving to a peaked wood ceiling, we are able to eliminate that unused attic space. That means that without much change to the interior dimensions, we are lowering the exterior significantly. It also means a single row of windows rather than a large and small row. The eaves will still be about 24' high with the roof rising from there; I don't think anyone will call this a short building.
I think a finished wood ceiling with attractive beam work will be very beautiful. I look forward to sharing updated drawings with you as they become available.
We still have work to do and calculations are ongoing. Admittedly, this stage of our project has its frustrations, but overall I'm pleased with how it's going. Before we were looking at a stunning design and vaguely hoping we could achieve something like it on budget. Now, we've had to take some cost-reduction measures, but we're still looking at an amazing design. And now, we're much more certain that we're on track to achieve it.
Here's a very quickly produced sketch of the modification we've adopted. The walls are lower; the interior now extends up to the peak instead of being entirely within the height of the eaves. In this design the peak of the interior is actually several feet higher than with the vaults, but the outside height is reduced. This one change introduced a cascade of savings that were really needed to hit our budget.
Note: This sketch also reflects a look at a different transept window configuration. We've elected to stay with the rose window design there.
Monday, July 29, 2013
Contract awarded for pre-construction services
Poettker Construction of Breese, IL has been hired for pre-construction services. This will involve cost and constructability consultation, and two rounds of estimates to help us stay on budget. While we retain the option to put the project out to bid, it is presumed that Poettker Construction will continue in a Construction Management capacity throughout the project.
I'm very pleased to announce this partnership and look forward to working with Poettker Construction!
Monday, July 1, 2013
Final Schematic Floorplan: Bishop-approved!
Here's what we're building.
Compared to previous versions, you will note some significant changes. For one, seating capacity has been increased. By code, at 18" per seat, there are 445 seats in the church. Figuring for very generous and comfortable spacing, at 24" per seat, the figure is 345. We are very confident about this capacity being ample for our congregation.
You'll notice the confessional and the vesting sacristy have switched places. This was a request from Bishop Braxton, and I think it's clearly an improvement. Since our current liturgical practice is for the procession to begin from the rear of the nave, this is the logical place for the vesting sacristy. I also favor having the confessional up front where it is more visible and prominent as congregants prepare for Holy Mass. Perhaps the little green light showing the availability of a confessor will move some to a more frequent practice of this indispensable Sacrament.
A slight slope is currently shown in the nave, of about one foot over the whole length of the seating from the rear to the point where the transepts begin. This will not be uncomfortable for standing or even for processing with a casket on a rolling platform, but it will enhance visibility of the sanctuary from rearward seats. We would like to include this feature, but are awaiting information about the cost.
You will note a choir location on the north side of the rear of the nave. This was found by wide consensus to be the most desirable location once a choir loft was removed from consideration. This area will have chairs (with kneelers) instead of pews, allowing for greater flexibility in arrangement for the choir. Some sort of non-permanent riser installation is not out of the question.
The Baptistery is in the transitional space between the narthex and nave. This transition has been widened significantly. The location of the Baptismal font here strongly expresses the nature of Baptism as our "point of entry" into the Church!
Thursday, June 20, 2013
Soil borings completed - with good news.
Holcomb Foundation Engineering Co., Inc. of Carbondale has completed soil borings to test the ground under our building. The results were awaited with some suspense, as it is known that some sketchy stuff can be encountered in this area. We are building a large, heavy masonry structure and settlement is something that simply can not be risked. If the borings showed a high settlement potential, we would see a great deal of money go into foundation enhancements to compensate.
The news was good! Some excavation is indicated, but it doesn't seem to involve anything deep. This translates to a relatively standard foundation, probably slab-on-grade, with potentially some piers or similar elements as determined by our structural engineer. The very curious might do a quick search on "Vibro Stone Columns" for one possibility.
Saturday, May 4, 2013
3D model animation
Little girls will get tired of Disneyworld's "Small World" ride before I get tired of watching this. - Fr. B
Friday, May 3, 2013