Roof decking begun, full crew starting Monday
Monday March 30 will officially end our partial winter shut-down. Focus will be in wall framing and roofing, with masonry starting next week. You can see here some decking started on the East end.
Friday, December 12, 2014
Thursday, November 20, 2014
Tower Columns Arriving
Three of the four tower columns are on site with the fourth on the way. These are the longest components by far at eighty feet, and are arriving assembled. They reach to the top of the masonry portion of the tower. From there, an aluminum steeple will rise to the full height of about 150 feet. It will be impressive to see these columns standing up!
Thursday, November 13, 2014
Structural Steel Continuing
Erecting the steel has made for some great viewing. Things will start seeming slower while a great deal of welding is done. Sometime in the next few weeks we'll see the 80 foot verticals for the tower go up... that'll be something to see!
My favorite view is from the ball field side.
Welding up at the ridge line. These guys don't stop for rain or cold.
With decking and insulation board going on, the sacristies are starting to feel like rooms.
Wednesday, October 22, 2014
Thursday, October 16, 2014
Structural steel taking shape
You can see the south transept filling out and get a sense of the elevation of the church. That's architect Kevin Hogan in the foreground!