Thursday, July 3, 2014

Materials Selection

Working toward a mock-up panel for reference during metals and masonry. We've chosen a stone blend from Earthworks, and picked roofing and metals colors to harmonize. The guttering and the steeple spire will be the patina green color you see; a dark gray slate colored roof tile is pictured, a sample of the cast stone color for cap and buttress elements, and we're going to split the mock-up into two mortar colors to help choose.


Week 4 update: Foundations

De-watering is progressing in the basement area; it will probably take another week or two. Lately we've been watching the footings take shape on the east end.
The apse is outlined here in the background, facing south

North wall foundation ready to pour. East/Apse foundations built up in background.

Ample supervision was on hand for this pour on Tuesday after Mass.

The north side foundations extended

Monday, June 16, 2014

Window Salvage

Workers from Jacksonville Art Glass carefully remove and crate the stained glass from St. Francis Xavier Church for restoration and installation. Prayers with the people of the former St. Francis Parish!

Friday, June 13, 2014

Week 1 Friday update

Excavation for east footings. Will need to be inspected, then filled with a layer of rock, then concrete footings. 

De-watering pumps are working away! There's already a noticeable difference, but how long it will take to make the deep excavation possible is anyone's guess. Work remains focused on the east end until then.

Thursday, June 12, 2014

De-watering wells

Richardsville Drilling dropping the first of three de-watering wells

Continuing excavation on the west end, where the mechanical vault will be, requires some de-watering. This is accomplished by drilling wells and pumping down the water table. We're drilling three wells today and will get that started. It's hard to predict how long it will take to dry things up enough to work, so we'll just have to wait and see.

In the meantime, excavation and foundation work can proceed on the west end of the building, which is much shallower.

While it would have been ideal to avoid the necessity of de-watering, it was a contingency we expected and planned for. There is a considerable amount of money in the budget for exactly this. The bottom line is that excavation and foundation needs remain the highest-risk phase of the project, in terms of possible complications. But the status so far is that, while we aren't exactly seeing our best-case scenario, we haven't run into anything we haven't planned for.

Monday, June 9, 2014

Excavating Lake Kateri

Trucking by Hish Farms and Payne Farms... Thank you!  We're obviously hitting some water and soft sand. Not exactly a surprise; it can be dealt with. Don't fall in though. 

Friday, May 30, 2014

We've Begun!

We've got green lights from the diocese and all the submittals needed to begin the first phase of construction. Scott Phillips et al are working today tying rebar, with excavation to follow next week.

So mark it down, May 30th, 2014, the first day of construction work on St. Kateri Church.

!!!  *clink*  !!!