Monday, June 16, 2014
Window Salvage
Workers from Jacksonville Art Glass carefully remove and crate the stained glass from St. Francis Xavier Church for restoration and installation. Prayers with the people of the former St. Francis Parish!
Friday, June 13, 2014
Week 1 Friday update
Excavation for east footings. Will need to be inspected, then filled with a layer of rock, then concrete footings.
Thursday, June 12, 2014
De-watering wells
Richardsville Drilling dropping the first of three de-watering wells |
Continuing excavation on the west end, where the mechanical vault will be, requires some de-watering. This is accomplished by drilling wells and pumping down the water table. We're drilling three wells today and will get that started. It's hard to predict how long it will take to dry things up enough to work, so we'll just have to wait and see.
In the meantime, excavation and foundation work can proceed on the west end of the building, which is much shallower.
While it would have been ideal to avoid the necessity of de-watering, it was a contingency we expected and planned for. There is a considerable amount of money in the budget for exactly this. The bottom line is that excavation and foundation needs remain the highest-risk phase of the project, in terms of possible complications. But the status so far is that, while we aren't exactly seeing our best-case scenario, we haven't run into anything we haven't planned for.
Monday, June 9, 2014
Subscribe to:
Posts (Atom)